Company Announces Strong Progress in Meeting Construction Milestones
Company Reports Increased Customer Interest Resulting from The Inflation Reduction Act
CENTENNIAL, Colo.–(BUSINESS WIRE)–Westwater Resources, Inc. (NYSE American: WWR), an energy technology and battery-grade natural graphite development company (�Westwater or the Company), today announced its third quarter results for the period ended September 30, 2022 and provided an update on its Kellyton graphite plant currently under construction in east-central Alabama.
During the third quarter of 2022, Westwater continued construction activities related to Phase I of its Kellyton graphite plant, including receipt of additional long-lead equipment items and continued work on underground utilities, fire loop, foundations, and the manufacturing of plant buildings.
In October, the Company began erecting the first of five primary buildings, and members of management inspected and oversaw the testing and validation of critical long-lead equipment in advance of shipment.
Westwater continues its engagement with potential customers. The Company is working with approximately 40 potential customers across a number of markets including automotive companies and lithium-ion battery manufacturers. Westwater continues to provide new or additional samples at the request of potential customers. To date Westwater has sent samples to 27 potential customers. Westwater believes that the Inflation Reduction Act which sets a minimum domestic content threshold for the percentage of the value of applicable critical minerals contained in the battery of the electric vehicles, is beneficial to the domestic graphite industry and will provide additional benefit to the Company as it continues to engage with potential customers. Since the passing of the Inflation Reduction Act in August, the interest of Westwaters potential customers has intensified as Westwater moves towards its domestic production of battery-grade natural graphite materials.
The Westwater team continues its strong progress related to the construction of Phase I of our Kellyton graphite plant and is planning to begin testing and commissioning of Phase I mid-year 2023 and continuing into the second half of next year, said Chad Potter, President and CEO.
I am encouraged by the progress during the quarter, and I am especially proud that all this progress was accomplished by our team without a lost time safety incident.
We finished the third quarter with a cash balance of $100.3 million and a working capital balance of $80.1 million and remain on budget for Phase I of the Kellyton graphite plant at $202 million, said Steve Cates, CFO and VP-Finance. Since beginning construction of Phase I of the Kellyton graphite plant in the fourth quarter of 2021, we have incurred approximately $50.5 million of costs, comprised of $34.6 million in cash spent and the remainder included in the Companys working capital liabilities as of September 30, 2022.
Financial Summary
($ in thousands, Except Share and Per Share Amounts) | Q3 2022 | Q3 2021 | Variance |
Net Cash Used in Operations* | $(8,589) | $(13,040) | (34%) |
Net Cash Used in Investing Activities* | $(31,968) | $(31) | n/m |
Net Cash Provided by Financing Activities* | $25,572 | $81,715 | (69%) |
Product Development Expenses | $(257) | $(1,834) | (86%) |
General and Administrative Expenses | $(2,611) | $(2,189) | 19% |
Net Loss | $(3,453) | $(4,568) | (24%) |
Net Loss Per Share | $(0.07) | $(0.13) | (46%) |
Avg. Weighted Shares Outstanding | 47,462,656 | 34,331,778 | 38% |
* Presented on a year-to-date basis. |
Conference Call
Management will host a conference call to discuss these results on November 10, 2022, at 11:00 AM EST.
The dial-in numbers are:
Canada/USA TF: 1-800-319-4610
International Toll: +1-604-638-5340
Callers should dial in 5-10 min prior to the scheduled start time and simply ask to join the call.
A live webcast of the conference call presentation will also be available at www.westwaterresources.net
For a replay of the call:
Canada/USA TF: 1-855-669-9658
International Toll: +1-412-317-0088
Replay Access Code: 9457
About Westwater Resources, Inc.
Westwater Resources, Inc. (NYSE American: WWR), an energy technology company, is focused on developing battery-grade natural graphite. The Companys primary project is the Kellyton graphite processing plant that is under construction in east-central Alabama. In addition, the Companys Coosa graphite deposit is the most advanced natural flake graphite deposit in the contiguous United States and located across 41,965 acres (~17,000 hectares) in Coosa County, Alabama. For more information, visit www.westwaterresources.net.
Cautionary Statement Regarding Forward-Looking Statements
This news release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as “expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” intensified, scheduled, targets and other similar words. Forward looking statements include, among other things, statements concerning the construction and operation of the Companys Kellyton graphite plant, the Companys Coosa graphite deposit, and the costs and schedules associated with them. The Company cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of the Company; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Westwaters Annual Report on Form 10-K for the year ended December 31, 2021, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: (a) the spot price and long?term contract price of graphite (both flake graphite feedstock and purified graphite products) and vanadium, and the world-wide supply and demand of graphite and vanadium; (b) the effects, extent and timing of additional competition in the markets in which we operate; (c) the ability to obtain contracts with customers; (d) available sources and transportation of graphite feedstock; (e) the ability to control costs and avoid cost and schedule overruns during the development, construction and operation of the Kellyton graphite plant; (f) the ability to construct and operate the Kellyton graphite plant in accordance with the requirements of permits and licenses and the requirements of tax credits and other incentives; (g) effects of inflation and rising interest rates; (h) the availability and supply of equipment and materials needed to construct the Kellyton graphite plant; (i) stock price volatility; (j) government regulation of the mining and manufacturing industries in the United States; (k) unanticipated geological, processing, regulatory and legal or other problems we may encounter; (l) the results of our exploration activities at the Coosa graphite deposit, and the possibility that future exploration results may be materially less promising than initial exploration results; (m) any graphite or vanadium discoveries at the Coosa graphite deposit not being in high enough concentration to make it economic to extract the metals; (n) our ability to finance growth plans; (l) the potential effects of the continued COVID-19 pandemic; (o) currently pending or new litigation or arbitration; and (p) our ability to maintain and timely receive mining, manufacturing, and other permits from regulatory agencies.
Contacts
Westwater Resources, Inc.
Email: Info@WestwaterResources.net
Product Sales Contact:
Jay Wago, Vice President Sales and Marketing
Phone: 303.531.0472
Email: Sales@westwaterresources.net
Investor Relations
Porter, LeVay & Rose
Michael Porter, President
Phone: 212.564.4700
Email: Westwater@plrinvest.com
Providing High-end Imaging Services: Establishing a New Benchmark for Personalized Medical Imaging Services HONG KONG…
JAKARTA, INDONESIA - Media OutReach Newswire - 22 November 2024 - VinFast Auto has officially…
SYDNEY, AUSTRALIA - Media OutReach Newswire - 22 November 2024 - The global cryptocurrency market…
HANOI, VIETNAM – Media OutReach Newswire - 22 November 2024 - By capitalizing on its…
HANGZHOU, CHINA - Media OutReach Newswire - 22 November 2024 - As the 2024 World…
BEIJING, CHINA - Media OutReach Newswire - 22 November 2024 - The 2024 Beijing Changping…