Categories: Wire Stories

Rio Tinto to triple Weipa solar capacity and add battery storage to help power operations

MELBOURNE, Australia–(BUSINESS WIRE)–Rio Tinto has approved a new solar farm and battery storage at Weipa in Queensland, in a move that will more than triple the local electricity network�s solar generation capacity and help provide cleaner power to Rio Tinto’s operations.

Under the plans, EDL has been contracted to build, own and operate a 4MW solar plant and 4MW/4MWh of battery storage at Weipa. Work on the battery facilities will start this year, with construction of the whole project expected to be complete by late 2022.

The new solar farm and battery storage will complement the existing 1.6MW solar farm at Weipa, which was completed in 2015 and is also owned and operated by EDL. The 4MWh battery system will be built next to the existing Weipa power station and will help provide a stable power network for Rio Tinto’s Weipa Operations bauxite mines and the Weipa township.

Rio Tinto Aluminium Pacific Bauxite Operations General Manager Michelle Elvy said “The new solar farm and battery storage at Weipa will help us lower our carbon footprint and diesel use in a reliable way.

“The original Weipa solar farm was the largest solar facility at an off-grid Australian mine site at the time it was built, and it played an important role in showing the viability of renewable energy systems in remote locations.

“The new solar farm and battery storage system is part of Rio Tinto’s group-wide commitment to reduce emissions across our operations. There is clearly more work to be done, but projects like this are an important part of meeting our climate targets.”

EDL Chief Executive Officer James Harman said “We welcome the opportunity to continue supporting Rio Tinto to reduce carbon emissions.

“EDL will be leveraging expertise from our hybrid renewable energy systems around Australia to deliver clean and reliable energy for Rio Tinto’s operations and the local community.”

When complete, the combined 4MW solar capacity and 4MW/4MWh battery will provide about 11 gigawatt hours of energy annually. Combined with upgrades to the existing Weipa power generation network, the improvements will reduce Weipa Operations’ diesel consumption by an estimated 7 million litres per year and lower its annual carbon dioxide emissions by about 20,000 tonnes – the equivalent of taking more than 3,750 cars off the road.

Rio Tinto Weipa Operations will purchase electricity from EDL and the new solar plant will be connected directly to the Weipa electricity network.

More information on Rio Tinto’s climate targets can be found here.

riotinto.com

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK
Illtud Harri
M +44 7920 503 600

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Rio Tinto plc
6 St James’s Square

London SW1Y 4AD

United Kingdom

T +44 20 7781 2000

Registered in England

No. 719885

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, Australia
Natalie Worley
M +61 409 210 462

Amar Jambaa
M +61 472 865 948

Rio Tinto Limited
Level 7, 360 Collins Street

Melbourne 3000

Australia

T +61 3 9283 3333

Registered in Australia

ABN 96 004 458 404

Category: Weipa

Alex

Recent Posts

Cheers to New Beginnings: Carlsberg Hong Kong Launches No & Low-Alcohol and Beyond Beer Series for Conscious Celebrations

Ringing in the New Year, the extended collection promotes moderation and conscious drinking throughout the…

47 minutes ago

The 27th Mountain Emei Ice, Snow & Hot Spring Season Invites Global Visitors to “Enjoy Winter Fun”

EMEISHAN, CHINA - Media OutReach Newswire - 16 December 2025 - On the evening of…

1 hour ago

Lily Allen, Little Simz and Bianca Bustamante Light Up The Red-Carpet In Desert Diamonds, At The Fashion Awards 2025

LONDON, UK - Media OutReach Newswire - 16 December 2025 - Desert diamonds graced the…

1 hour ago

ISCA Unveils Bold Plan to Future-Proof Singapore’s Small and Medium-Sized Accounting Practices

SINGAPORE - Media OutReach Newswire - 16 December 2025 - Small and Medium-Sized Accounting Practices…

5 hours ago

Leeds Capital and MIO Trust Are Proud to Announce Their Collaboration on an AI‑Driven Multi‑Asset Trust Focused on Digital Assets and Precious Metals

SYDNEY, AUSTRALIA - Media OutReach Newswire - 16 December 2025 - Leeds Capital and MIO…

6 hours ago

Optimistic Hong Kong Ecommerce Merchants Report Growth, But Hidden Payment Friction Is Eroding Up to 10% of Revenue, Aspire Report Finds

Despite 64% reporting revenue growth, 91% of merchants face payment friction HONG KONG SAR -…

6 hours ago