(All amounts in US$ unless otherwise specified)
VANCOUVER, British Columbia–(BUSINESS WIRE)–#capstonemining–Capstone Mining Corp. (“Capstone” or the “Company”) (TSX:CS) announces its production and financial results for the three months (“Q1 2020”) ended March 31, 2020. Copper production totaled 35.5 million pounds of copper at consolidated C1 cash costs1 of $2.05 per payable pound produced.
“I am proud of Capstone’s response to the COVID-19 pandemic. Our top priority is to ensure the health of our employees and our communities in which we operate, while maintaining the health of our business,” said Darren Pylot, President & CEO of Capstone. “Our quick mitigation measures positioned Capstone to weather this current low copper price environment without delaying the 2021 growth targets we have set.”
“We were well positioned to face the abrupt economic downturn during Q1 2020, having cut nearly $30 million in annual costs from the business last year,” said Raman Randhawa, SVP & CFO of Capstone. “We were fortunate to have the flexibility to defer another $32 million in capital costs this year, while having preserved multiple levers that could be triggered to increase liquidity, if necessary. Also, we have taken actions on additional operating cost savings of $22 million which include locking in contract purchases and hedges on very low diesel prices, transportation and the Mexican Peso for the remainder of 2020. This is expected to result in consolidated C1 operating costs and all-in sustaining costs of ~$1.80 and ~$2.20 per pound, respectively, for the balance of this year.”
COZAMIN UPDATE
On April 7, the Company safely commenced ramping down operations at Cozamin to comply with a Mexican Federal Government decree which was extended from April 30, 2020 to until May 30, 2020. The decree allows for normal operations to resume on May 18, 2020 in municipalities which present low or null transmission of COVID-19. Zacatecas is a low-risk jurisdiction based on current statistics. The Company is taking all steps necessary to be able to quickly and safely ramp production back up to full capacity by May 18, 2020.
Q1 2020 HIGHLIGHTS AND SIGNIFICANT ITEMS
CORPORATE UPDATE
COVID-19
In response to the World Health Organization declaring novel coronavirus (COVID-19) a global pandemic in early March, Capstone has taken the following measures to ensure the health and safety of our people and the communities in which we operate:
2020 Cost Reductions
At the end of December 2019, the Company achieved its target of sustainable annualized cost savings of $27.5 million from the business, using 2018 as a baseline.
In response to COVID-19, Capstone has taken prudent financial measures to reduce discretionary capital and exploration expenditures by $32 million in 2020.
In addition, in relation to current financial markets, the Company is targeting the following cost reductions in 2020 expected to be reflected in our future operating results. These are additional cost saving measures which would enable Capstone to reduce our cash operating costs by approximately $22 million over the remainder of 2020.
Operating Cost Items |
Projected Annualized |
Projected 2020 Savings |
Diesel | $10 | $8 |
Transportation costs | $3 | $2 |
Contractor management freeze | $4 | $3 |
Consumables and other inputs costs | $4 | $3 |
Mexican peso @ 24.00 versus guidance 19.50 | $5 | $4 |
Canadian dollar @ 1.40 versus guidance 1.30 | $1 | $1 |
Fixed interest rate swap | $1 | $1 |
TOTAL | $28 | $22 |
Pinto Valley Cost Reductions
As a result of these cost reduction measures and expected improvements to production compared to Q1 2020 (primarily related to grades reverting back to average of 0.31% copper), we expect the C1 cash costs1 for Pinto Valley to reduce dramatically in the remaining quarters in 2020, compared to Q1 results, to below $2.00/lb. This is a result of the following key factors illustrated in the waterfall chart. (Refer to the Risks and Uncertainties section in Capstone’s Q1 2020 Management’s Discussion and Analysis (“MD&A”) and Financial Statements for updated COVID-19 related risks.)
Pinto Valley: PV3 Optimization
PV3 Optimization is an initiative that aims to enhance performance via a series of low capital, quick payback, high impact debottlenecking steps and operational tweaks. The goal is to sustainably boost throughput, enhance recovery and lower costs. All required permits are in place to operate at levels up to 79,500 tonnes per day.
The first phase of PV3 Optimization aims to increase reliability and improve performance in the fine crushing plant and grinding circuit (“Phase 1”). In Q1 2020, the first of two secondary crushers and screen decks arrived and are scheduled to be installed in July. Also in July, the first of two new ball mill shells are expected to be installed, with the second scheduled for Q1 2021. The second secondary crusher and six tertiary screen decks are scheduled to arrive in Q4 2020. Once completed, the expected result is for throughput to reliably achieve higher throughput levels in the 56,000 to 57,000 tonnes per day range in 2021. During Q1 2020, a mineral processing consultant was hired to assist in reviewing historical reports and operational data and identify operational improvements to advance in the short term (“Phase 2”).
Pinto Valley: PV4 Expansion
Preliminary work on Pinto Valley’s potential future expansion to 100,000+ tonnes per day (“PV4 Expansion”) continues but at a slower rate given COVID-19 restrictions. The update has been delayed for an indeterminate period. The study is focused on evaluating potential scenarios to take advantage of the one billion tonnes of Mineral Resources not currently scheduled in the current mine plan pit shell (“PV3”).
Cozamin: Near-Term Expansion Update
In early April 2020, Cozamin completed two major projects that represent a significant achievement on our path to expanding copper and silver production in 2021. The final key component of this expansion, the Calicanto one-way ramp, continues as scheduled and on budget to be completed in December 2020. (Refer to the Risks and Uncertainties section in Capstone’s Q1 2020 MD&A and Financial Statements for updated COVID-19 related risks.) The 818-meter raisebore was completed 52 days ahead of schedule, which immediately improved ventilation and decreased the temperature in the deepest area of the mine. The second milestone is completion of an upgrade to the underground electrical substation, to boost the mine from 7.5MW to 9.5MW. In addition, an additional underground maintenance shop has been completed, increasing fleet maintenance capacity by 50%. Once completed, the underground expansion is expected to increase production to a new annual run rate of approximately 50-55 million pounds of copper and 1.5 million ounces of silver in 2021.
Cozamin: Targeting Doubling Mine Life
Updated Mineral Resource and Mineral Reserve estimates for Cozamin are still expected to be completed in late 2020. The 2019/2020 step-out and infill drilling program was progressing well at 85% completed and approximately three months ahead of schedule, until it was suspended as a non-essential activity by Mexican national decree. The drilling completed to date will be used to upgrade Inferred Mineral Resources to the Indicated category and subsequent conversion to Mineral Reserves to target doubling the mine life. Positive drill results pointing to higher grades and wider intercepts than in the current Mineral Reserve estimates were released on January 16, 2020 and April 23, 2020.
Santo Domingo Technical Report Update
In February 2020, a positive update to Santo Domingo’s Feasibility Study-level Technical Report, originally published on January 3, 2019 (“Base Case”), was released on February 19, 2020 and filed on SEDAR on March 24, 2020. The update included a higher level of Capital (“CAPEX”) and Operating Cost (“OPEX”) certainty, receipt of additional key permits and the development of a Preliminary Economic Assessment with respect to cobalt production (the “2020 PEA Opportunity”). Highlights included:
OPERATIONAL OVERVIEW
Refer to Capstone’s Q1 2020 MD&A and Financial Statements for detailed operating results.
| Q1 2020 | Q1 2019 |
Copper production (million pounds) |
|
|
Pinto Valley | 26.8 | 32.7 |
Cozamin | 8.7 | 8.7 |
Total copper production (million pounds) | 35.5 | 41.4 |
Copper sales |
|
|
Total copper sales (from continuing operations)2 (million pounds) | 30.4 | 35.3 |
Realized copper price ($/lb.) | $2.29 | $2.99 |
C1 cash costs1 ($/lb.) produced |
|
|
Pinto Valley | $2.41 | $1.79 |
Cozamin | $0.95 | $0.70 |
Consolidated C1 cash costs1 ($/lb.) produced | $2.05 | $1.56 |
1 This is an alternative performance measure; please see “Alternative Performance Measures” at the end of this release. |
2 Sales from continuing operations has been utilized due to the Minto mine being classified as a discontinued operation in the comparative period until the point of its sale on June 3, 2019. |
Consolidated
Production of 35.5 million pounds was at the lower end of the original guidance range of 140 to 155 million pounds. Production levels are expected to ramp up through the year as Pinto Valley mined a lower grade area of the upper portion of the pit during the quarter. A focus on maximizing mill throughput continued in Q1 2020 following the successful December 2019 operational test, announced with the 2019 results in February 2020. A total of 28 days of over 60,000 tonnes per day was realized during Q1 2020 and an average daily throughput rate during Q1 2020 of 54,900 tonnes per day, or approximately 5% higher than the three-year average from 2017 to 2019. Sustainable high mill throughput rates are expected in the second half of 2020, helped by the installation of the first of two secondary crushers and screen decks planned for July 2020. Recoveries during the quarter of 82.4% were impacted by the low feed grade of 0.284% plus an expected higher than average oxide component. Grade and recovery are both planned to be higher for the balance of the year.
C1 cash costs1 were impacted by Pinto Valley costs, overall lower production and less capitalized stripping resulting from the increased ore delivery to the mill.
The realized copper price in Q1 2020 of $2.29 per pound was lower than the LME average of $2.56 per pound due to three provisionally priced shipments at March 31, 2020, which were priced at an average of $2.24 per pound. In addition, there was a ($0.10) per pound negative provisional adjustment on prior shipments due to copper prices decreasing throughout the quarter. Sales volumes in Q1 2020 were lower than production due to timing of shipments at Pinto Valley.
Pinto Valley Mine
C1 cash costs1 of $2.41 per pound in Q1 2020 were higher than Q1 2019, primarily due to 18% lower copper production compared to the same period last year, as well as higher operating costs (site costs were $56 million in Q1 2020 compared to $216 million in 2019 or a run rate of $54 million per quarter). C1 cash costs1 were also impacted by lower capitalized stripping in Q1 2020 of $5.3 million or $0.20 per pound.
Property cost per tonne milled1 of $10.87 was $0.30/tonne lower (-3%) versus the average cost per tonne milled in 2019 and $0.76/tonne lower (-6.5%) than in 2018. This reflects the cost cuts implemented over the course of last year.
During Q1 2020, the mill was able to achieve mill throughput of 54,899 tonnes per day (highest quarterly total since Q4 2017) as a result of operational improvements tied to maintenance programs.
Cozamin Mine
Production in Q1 2020 remained consistent at Cozamin compared to Q1 2019. C1 cash costs1 of $0.95 per pound were higher than Q1 2019. The primary cause of this is a decrease in by-product credits during the quarter due to declining commodity prices as a result of current market conditions, as well as less San Rafael zinc ore mined during the quarter. This was offset by decreases in overall operating costs from cost management efforts, as well as lower treatment and selling costs.
FINANCIAL OVERVIEW
Refer to Capstone’s Q1 2020 MD&A and Financial Statements for detailed financial results.
| Q1 2020 | Q1 2019 |
Revenue2 ($ millions) | 70.4 | 108.9 |
Net income (loss) ($ millions) | (21.9) | 8.3 |
Adjusted net income (loss)1($ millions)3 | (17.7) | 12.0 |
Adjusted EBITDA1,4 from continuing operations2,3 ($ millions) | 11.1 | 35.6 |
Cash flow from operating activities2 ($ millions) | 6.9 | 28.7 |
Operating cash flow before changes in working capital1,2 ($ millions) | (3.5) | 30.7 |
|
March 31, |
December 31, |
Total assets ($ millions) | 1,309.9 | 1,331.4 |
Long term debt (excluding financing fees) ($ millions) | 219.9 | 209.9 |
Net debt1 ($ millions) | 188.0 | 165.5 |
1 This is an alternative performance measure; please see “Alternative Performance Measures” at the end of this release. |
2 In accordance with IFRS 5, Minto’s results are excluded from revenue but included within cash flow amounts in the comparative period. The Minto mine was sold on June 3, 2019. |
3 Certain prior period amounts have been restated to conform with current period classification. |
4 EBITDA is earnings before interest, taxes, depletion and amortization. |
OUTLOOK – 2020 PRODUCTION, COST AND CAPITAL GUIDANCE
In light of the temporary ramp-down at Cozamin to comply with a Mexican Federal Government decree which was extended from April 30, 2020 to until May 30, 2020, and the ongoing uncertainty regarding COVID-19, Capstone has decided to withdraw its full-year 2020 production guidance. The Company will continue to target safe execution of its operation plans and will re-evaluate its full-year 2020 guidance as the pandemic evolves.
Prior to the temporary ramp-down at the Cozamin mine, Capstone had taken prudent financial measures, due to the recent drop in copper prices, to reduce discretionary capital and exploration expenditures of $32 million in 2020, as shown in the table below. The Company does not expect that these reductions will materially impact its growth plans for 2021 and beyond.
Refer to the Corporate Update section for revised 2020 operating cost expectations.
2020 Expenditure Guidance | Original Guidance | Revised Guidance |
Pinto Valley |
|
|
Sustaining | $28 | $18 |
Capitalized stripping | $8 | $3 |
Expansionary | $19 | $12 |
Total Pinto Valley Capital | $55 | $33 |
Cozamin | $26 | $24 |
Santo Domingo | $93 | $64 |
Total Capital | $90 | $63 |
Total Exploration | $10 | $5 |
3 On a 100% basis, the figure is $12 million; ownership is 70% Capstone and 30% Korea Resources Corporation. |
4 On a 100% basis, the figure is $9 million; ownership is 70% Capstone and 30% Korea Resources Corporation. |
CONFERENCE CALL AND WEBCAST DETAILS
Date: | Wednesday, April 29, 2020 | |
Time: | 11:30 am Eastern Time (8:30 am Pacific Time) | |
Dial in: | North America: 1-877-823-8676, International: +825-312-2240 | |
Webcast: | https://event.on24.com/wcc/r/2218097/7C9FE2184A36B0D28729C5A8FBF1B50B | |
|
| |
The conference call replay will be available until May 13, 2020. | ||
Replay: | North America: 800-585-8367, International: +416-621-4642 | |
Passcode: | 5215689 | |
|
| |
Following the replay, an audio file will be available on Capstone’s website at https://capstonemining.com/investors/events-and-presentations/default.aspx. |
This release is not suitable on a standalone basis for readers unfamiliar with Capstone and should be read in conjunction with the Company’s MD&A and Financial Statements for the three months ended March 31, 2020, which are available on Capstone’s website and on SEDAR, all of which have been reviewed and approved by Capstone’s Board of Directors.
1 This is an alternative performance measure; please see “Alternative Performance Measures” at the end of this release.
ABOUT CAPSTONE MINING CORP.
Capstone Mining Corp. is a Canadian base metals mining company, focused on copper. We are committed to the responsible development of our assets and the environments in which we operate. Our two producing mines are the Pinto Valley copper mine located in Arizona, US and the Cozamin copper-silver mine in Zacatecas State, Mexico. In addition, Capstone has the large scale 70% owned copper-iron Santo Domingo development project in Region III, Chile in partnership with Korea Resources Corporation, as well as a portfolio of exploration properties. Capstone’s strategy is to focus on the optimization of operations and assets in politically stable, mining-friendly regions, centred in the Americas. Our headquarters are in Vancouver, Canada and we are listed on the Toronto Stock Exchange (TSX). Further information is available at www.capstonemining.com.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION
This document may contain “forward-looking information” within the meaning of Canadian securities legislation and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, “forward-looking statements”). These forward-looking statements are made as of the date of this document and the Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required under applicable securities legislation.
Contacts
Jerrold Annett, VP, Strategy and Capital Markets
647-273-7351
jannett@capstonemining.com
Virginia Morgan, Manager, IR and Communications
604-674-2268
vmorgan@capstonemining.com
HANOI, VIETNAM - Media OutReach Newswire - 26 December 2024 - While the EV industry…
Singaporeans are invited to nominate their “Real Ones” to celebrate those who embody responsibility who…
BANGKOK, THAILAND – Media OutReach Newswire – 26 December 2024 - PTT Global Chemical Public…
HONG KONG SAR – Media OutReach Newswire – 26 December 2024 - ALCO HOLDINGS (00328)…
MOSCOW, RUSSIA - Media OutReach Newswire - 26 December 2024 –The rating agency China Chengxin…
HONG KONG SAR – Media OutReach Newswire – 25 December 2024 - On December 14th,…